PT Pertamina EP through PT Pertamina EP Asset 2 immediately operates the production facilities of GAC Pump Station (SPG) Paku Gajah and SPG Kuang. The operation of both SPG is part of the Paku Gajah Development Project (PGDP) in Muara Enim and Ogan Komering Ilir, South Sumatra.
Nanang Abdul Manaf, President Director of Pertamina EP, said that PGDP is a gas field development project around Pagardewa, Kuang and Paku Gajah, which is located in Muara Enim Regency and Ogan Komering Ulu Regency, South Sumatera Province.
"The current status of PGDP has been the handover of the SPG Paku Gajah facility with a capacity of 45 mmscfd and SPG Kuang with a capacity of 25 mrnscfd to PT Pertamina EP Asset 2," he said in a release on Monday (31/7).
The Paku Gajah project currently uses the complete production facility of Early Production Facility (EPF). Starting from producing natural gas from exploration wells and development wells that have been drilled since 2010.
The Paku Gajah development project will have a 12-inch truckline line along the 23 km. The pipe extends from SPG Paku Gajah to existing CO2 removal of SPG Merbau. Furthermore, the gas produced from SPG Paku Gajah and SPG Kuang will be distributed to consumers of PT Perusahaan Gas Negara Tbk (PGAS) and other gas consumers in South Sumatra.
IN INDONESIA
Pertamina EP Menyerahkan Aset Paku Gajah dan Kuang
PT Pertamina EP melalui PT Pertamina EP Asset 2 segera mengoperasikan fasilitas produksi Stasiun Pengumpul Gas (SPG) Paku Gajah dan SPG Kuang. Pengoperasian kedua SPG tersebut bagian dari Paku Gajah Development Project (PGDP) di Muara Enim dan Ogan Komering Ilir, Sumatra Selatan.
Nanang Abdul Manaf, Direktur Utama Pertamina EP mengatakan, PGDP adalah proyek pengembangan lapangan gas di sekitar Pagardewa, Kuang dan Paku Gajah, yang berada di Kabupaten Muara Enim dan Kabupaten Ogan Komering Ulu, Provinsi Sumatera Selatan.
"Status saat ini PGDP sudah serah terima fasilitas produksi SPG Paku Gajah berkapasitas 45 mmscfd dan SPG Kuang dengan kapasitas 25 mrnscfd ke PT Pertamina EP Asset 2," kata dia, dalam rilis, Senin (31/7).
Proyek Paku Gajah saat ini menggunakan fasilitas produksi Early Production Facility (EPF) sewa lengkap. Mulai dari memproduksi gas bumi dari sumur-sumur eksplorasi maupun sumur pengembangan yang telah dibor sejak tahun 2010.
Proyek pengembangan Paku Gajah nantinya memiliki jalur pipa truckline 12 inci sepanjang 23 km. Pipa tersebut terbentang dari dari SPG Paku Gajah ke CO2 removal eksisting SPG Merbau. Selanjutnya, gas yang dihasilkan dari SPG Paku Gajah dan SPG Kuang tersebut akan disalurkan ke konsumen PT Perusahaan Gas Negara Tbk (PGAS) maupun konsumen-konsumen gas lain di daerah Sumatra Selatan.
Kontan, Page-14, Tuesday, August 1, 2017