SKK Migas Seeks 12 Oil and Gas Projects This Year is Not Delayed



The Special Task Force for Upstream Oil and Gas Business Activities (SKK Migas) seeks to prevent 12 oil and gas projects scheduled to start production this year due to the widespread of the Corona Virus.

Dwi Soetjipto

SKK Migas Head Dwi Soetjipto said that the Covid-19 pandemic, which was followed by a call for the community to remain at home, made the oil and gas operational schedule for the project shifted from the plan. From his observation, there is one oil and gas project which has the potential to be delayed from this year's operation to next year.

"But we are trying to minimize the shift. We will inform you more fully in mid-April, "he said.

SKK Migas

SKK Migas Deputy for Operations Julius Wiratno added that the oil and gas project development has the potential to be disrupted due to a change in crew and logistics supply. Nevertheless, he will continue to conduct intensive coordination to mitigate and carry out recovery plans for the oil and gas project. In fact, several projects he said had been operating.

Blogger Agus Purnomo in SKK Migas

"Of the 12 projects in 2020, there are already four projects that are on stream (starting operations), all according to schedule. Hopefully, everything can run smoothly, "he said.

Of these four projects, three are scheduled to be operational in the first quarter of 2020, namely the Grati Pressure Lowering Project with a capacity of 30 million cubic feet per day / mmscfd by Ophir Indonesia (Sampang) Pty Ltd, Buntal-5 45 mmscfd by Medco E&P Natuna Ltd, and Sembakung Power Plant by PT Pertamina EP.



While one more project was completed earlier than planned in the second quarter, the Randu Scissors Project with an estimated production of 3 mmscfd by PT Pertamina Hulu Energi Randu Gunting. In addition, there are eight other projects planned to operate this year.

Blogger Agus Purnomo in Petronas Carigali Ketapang

In the first quarter, Bukit Tua Phase-3 with an estimated production of 31.5 mmscfd by Petronas Carigali Ketapang II Ltd is planned to start operations. Furthermore, three projects will operate in the second quarter, namely 15 mmscfd Betung Compressors by PT Pertamina EP, Malacca Strait Phase-1 3,000 bpd by EMP Malacca Strait, and Meliwis 20 mmscfd by Ophir Indonesia (Madura Offshore) Pty Ltd.

In the third quarter of 2020, there were three oil and gas projects scheduled to operate. These three projects are the 2.4 mmscfd Beauty Project by PT Sele Raya Belida, the 150 mmscfd LP-MP Compressor by PT Pertamina EP, and Peciko 8A 8 mmscfd by PT Pertamina Hulu Mahakam. Finally, the Merakes Project by ENI Indonesia is scheduled to begin production in the fourth quarter of 2020. 

ENI

At the Merakes Field, ENI plans to drill six subsea wells and build an underwater pipeline system that will be connected to the floating cricket production facilities / Jangkrik FPU in Muara Bakau Block. The peak production of the Merakes Field is estimated to reach 60,305 barrels of oil equivalent per day / boepd.

the Merakes Field

In 2020, the national oil and gas lifting is set at 1.95 million barrels of oil equivalent per day / boepd, up slightly from last year's realization of 1.8 million boepd. Specifically, oil production rose to 755 thousand BPD from the realization of 746 thousand BPD, and gas to 1.19 million boepd from the realization of 1.06 million boepd.

Investor Daily, Page-9, Friday, March 27, 2020