Drilling according to Plan, JTB Project Starts Operating Next Year



PT Pertamina EP Cepu (PEPC) has completed the completion of four oil and gas wells in the Jambaran-Tiung Biru Field (JTB). This subsidiary of PT Pertamina (Persero) will complete drilling of two more wells so that the JTB Project can start operating in 2021.

the Jambaran-Tiung Biru Field (JTB)

Director of PT Pertamina EP Cepu (PEPC) Jamsaton Nababan said the completion phase was an important step in the development of the Jambaran-Tiung Biru Gas Field well. Because the well has entered the final phase before then producing gas.

"We hope that this continued operation can take place safely and smoothly, in accordance with our commitment to safety standards. We hope that the JTB project will run safely, safely and smoothly until the target on stream is achieved by 2021, "he said.

RIG PDSI

The completion of the four wells at Wellpad Jambaran East runs from 6 April to 25 May. At this stage, the production pipeline is installed and all its accessories, including the X-Mass Tree, are used to regulate the gas production flow.

RIG PDSI # 40

The four wells are JAM-3, JAM-4ST, JAM-5ST, and JAM-8. The perforation work will later be done without using a rig. Drilling Operations Manager Dhanar Eko Prasetyo added, his party then moved the rig to Jambaran Central Wellpad once the completion of four wells in Jambaran East was completed on May 25. Subsequently, drilling of two wells in Jambaran Central, namely JAM-6 and JAM-7, began this June.

"In carrying out the work, we ensure the safety of every worker involved. Safe working hours at the Drill Site have reached 934,830 as of May 8, 2020, "he said.

Safe working hours are an important part of the JTB Project operated by PEPC. In total, PEPC has reached 17,391,921 Safe Working Hours. Previously, Pertamina EP Cepu had successfully completed the installation of the Selexol Regenerator and Absorber. 

    In addition, the company has also completed detailed design work (front end engineering design / FEED), land acquisition, and early civil work. In addition to Well drilling, Pertamina EP Cepu is also still working on gas / GPF processing facilities construction and well drilling.

Investor Daily, Page-10, Tuesday, June 2, 2020