SKK Migas Accelerates Three Oil and Gas Projects



The Special Task Force for Upstream Oil and Gas Business Activities (SKK Migas) accelerated the operational schedule of the three national upstream oil and gas projects to this year at the time of mobility restrictions due to Covid-19. The three projects will increase oil production by 3,000 barrels per day and gas by 5 million cubic feet per day / MMSCFD.



SKK Migas Deputy for Operations Julius Wiratno said the three oil and gas projects were the development of the Big Bamboo Project and the construction of the Sembakung gas compressor facility by PT Pertamina EP, and the reactivation of the PHE-12 platform by PT Pertamina Hulu Energi West Madura Offshore (PHE-WMO). These three projects should only be completed next year.

Blogger Agus Purnomo in PHE-WMO

"But these projects can be completed by 2020," he said.

He explained the Big Bamboo Block Project would produce gas of 3 mmscfd. At present, the project is still in the stage of working on the engineering, procurement, and construction / EPC package and will go on stream in the third quarter of this year. While reactivation of the PHE-12 platform is an improvement activity that was skewed in 2017 ago.

This project is targeted to be realized later this year and can produce oil of 3,000 BPD. Furthermore, the Sembakung compressor project is also scheduled to be completed by the end of 2020 and will produce 2 MMSCFD of gas.

"The success in accelerating the realization of the upstream oil and gas project when the mobility restrictions in the context of Covid-19 mitigation shows the determination and enthusiasm of the upstream oil and gas people to be able to implement the program agreed in the Work Program and Budget (WP&B) 2020 optimally and efficiently," said Julius.

Julius also revealed that the Meliwis Block Project undertaken by Ophir Indonesia (Madura Offshore) will be completed and start operating this July. This project will produce a gas of 20 MMSCFD.

Dwi Soetjipto

The Head of SKK Migas, Dwi Soetjipto appreciated the innovations made by his ranks with the cooperation contract contractors (KKKS) so as to produce an acceleration of projects in the field. He continues to coordinate with KKKS to ensure that the upstream oil and gas project can run well according to schedule.

"During the Covid-19 outbreak, SKK Migas was able to accelerate the implementation of the completion of three projects," he said.

According to him, if the upstream oil and gas project can run well, there will be an increase in the production and production of oil and gas lifting. In addition, the oil and gas project is also able to move the regional economy and create jobs, especially the community around the project site.

"This is in line with the Government's focus on being able to encourage the economy to move during the Covid-19 outbreak," he added.

Dwi acknowledged the Covid-19 outbreak and the still low oil prices were a real test for efforts to realize the oil production target of 1 million BPD in 2030. One of the important keys to achieving the target was how to keep the project going well on schedule.

The success in accelerating the project was due to the successful implementation of the 2 pillars of the SKK Migas transformation, namely the Integrated Operation Center (IOC) and One Door Service Policy (ODSP).

Previously, four oil and gas projects were operating. First, the Grati Pressure Lowering Project in East Java was undertaken by Ophir Indonesia (Sampang) Pty and produced 30 MMSCFD of gas. Then, the development of the Randugunting Field by PT Pertamina Hulu Energi (PHE) Randugunting in Central Java provided additional production of 5 MMSCFD.

Furthermore, the Buntal-5 Field by Medco E&P Natuna Ltd provides additional gas production of 45 MMSCFD. Finally, Sembakung Power Plant by PT Pertamina EP with a capacity of 4 MW to support upstream oil and gas operations in the East Kalimantan region.

Blogger Agus Purnomo in Petronas Carigali Ketapang II Ltd.

In 2020, SKK Migas targets 11 upstream oil and gas projects to be onstream. Another project scheduled to operate this year is Bukit Tua Phase-3 with an estimated production of 31.5 MMSCFD by Petronas Carigali Ketapang II Ltd. planned to begin operations in the first quarter of last year.

Blogger Agus Purnomo in Petronas Carigali Ketapang II Ltd.

Furthermore, besides Meliwis, two projects will operate in the second quarter, namely the 15 MMSCFD Betung Compressor by PT Pertamina EP, Malacca Strait Phase-1 3,000 BPH by EMP Malacca Strait.

In the third quarter of 2020, there were three oil and gas projects scheduled to operate. These three projects are the 2.4 mmscfd Beauty Project by PT Sele Raya Belida, the LP-MP SKG-19 150 MMSCFD Compressor by PT Pertamina EP, and Peciko 8A 8 MMSCFD by PT Pertamina Hulu Mahakam.



Finally, the Merakes Project by ENI Indonesia is scheduled to begin production in the fourth quarter of 2020. The peak production of the Merakes Field is estimated to reach 60,305 barrels of oil equivalent per day / BOEPD. In 2020, national oil and gas lifting was set at 1.95 million BOEPD, up slightly from last year's 1.8 million boepd realization. 

the Merakes Project by ENI Indonesia

    Specifically, oil production rose to 755 thousand BPH from the realization of 746 thousand BPH, and gas to 1.19 million BOEPD from the realization of 1.06 million BOEPD.

Investor Daily, Page-10, Thursday, June 4, 2020