73 Wells Have Been Drilled


    Less than 2 months before the transfer of management of the Rokan Block from PT Chevron Pacific Indonesia (CPI) to PT Pertamina Hulu Rokan (PHR), a total of 73 wells have been drilled during the transition period.

Blogger Agus Purnomo in SKK Migas

    Deputy for Operations of the Special Task Force for Upstream Oil and Gas Business Activities (SKK Migas) Julius Wiratno explained that the progress of the transition process for Rokan's work area was still progressing according to the target.

"One of the priorities is to carry out development drilling to increase production, which currently has reached 73 wells that have been drilled and increase production," he said.

    Julius added that Chevron is trying to increase the number of rigs and long-lead items needed for well drilling activities in the Rokan Block to curb the decline in production during the transition period.

 
the Rokan Block 

    He also stated that all preparations from PT Pertamina Hulu Rokan (PHR) had been carried out. Thus, Pertamina is ready to carry out the transfer of management on August 9, 2021.

"Many programs such as the procurement of additional drilling rigs and offering employment are already around 100% completed," he explained.


    Previously, President Director of PT Pertamina Hulu Rokan (PHR) Jaffee A. Suardin said that one of the activities currently underway is the mirroring process for existing contracts which has reached 95% or 276 contracts out of 290 contracts.

"The process of procuring goods and services at PHR for the Rokan block is carried out by several methods, namely mirroring for existing contracts at PT Chevron Pacific Indonesia (CPI) and new procurement for contracts that are not yet in PT Chevron Pacific Indonesia (CPI) or mirroring cannot be done," he said.

    Apart from mirroring existing contracts and new procurements, there are also contracts through the Local Business Development (LBD) program. Currently, there are 260 LBD contracts that will be processed separately involving around 690 LBD partners. LBD phase 1 socialization was carried out at the end of last May and it is hoped that in the 3rd or 4th week of June the contract can be realized.

"PT Pertamina Hulu Rokan (PHR) will also evaluate opportunities to expand the involvement of the surrounding community by involving Village-Owned Enterprises (BUMdes)," he said.

Bisnis Indonesia, Page-4, Tuesday, June 22, 2021