google.com, pub-9591068673925608, DIRECT, f08c47fec0942fa0 All Posts - MEDIA MONITORING OIL AND GAS -->

MARKET

Wednesday, January 22, 2020

Asset 4 General Manager of PT Pertamina EP



Asset 4 General Manager of PT Pertamina EP, Agus Amperianto confirmed and committed to the implementation of safety in all operational activities. This was revealed during a field visit or Management Walktrough (MWT) in the Tapen field, Trucuk District, Bojonegoro Regency. 

Agus Amperianto

     During the visit, the Pertamina EP Asset 4 General Manager along with the Cepu Field management team ensured the achievement of the TPN-01 Gas well monetization project.

"From my observations in the field, the progress of the construction of the EPF is progressing smoothly and will be targeted for completion by the end of January 2020," Agus said.

Furthermore, Agus added, the purpose of this MWT was to ensure output from the TPN-01 monetization well project with a gas production target of 1.8 MMSCFD. With the monetization of gas from the wellhead, it is hoped that it will add revenue directly to Pertamina EP Asset 4 Cepu Field.

Blogger : Agus Purnomo in Pertamina EP Asset 4 Tuban

"Hopefully the spirit and motivation of Cepu Field workers in welcoming the performance targets for the 2020 Pertamina EP Asset 4 Cepu Field Work Plan," he said.

Blogger : Agus Purnomo in Pertamina EP Asset 4 Surabaya

Agus Amperianto said that the target of this plan is expected to be able to optimize the opportunities available to be executed properly, such as the gas monetization project that has been carried out at the Tapen well. Where the success of this project will support the achievement of the 2020 Cepu Field production target of 2,206 BOPD.

Blogger : Agus Purnomo in Pertamina EP Asset 4 Tuban

Nevertheless, even though they are aggressive in operating, they must ensure that safety aspects are carried out properly and Zero Incident is maintained according to the theme of the Pertamina EP K3 month 2020 "Build Safety Behavior? "As high as our production achievements, if there is a Safety Failure, then it all has no meaning. So let all of us both workers and work partners pay attention to aspects of Safety at work," explained Agus Amperianto.

Meanwhile, Cepu Field Manager, Afwan Daroni admitted, was ready to fully support the direction and targets that have been submitted by GM. He promised to be committed so that in 2020 the achievement of Pertamina EP Asset 4 Cepu Field can be better and improved compared to previous years.

"Certainly we at Cepu will also be committed according to the direction of Mr. GM," he explained.

IN INDONESIA

Asset 4 General Manager PT Pertamina EP Tekankan Agresive Production dan Safety Behaviour


Asset 4 General Manager PT Pertamina EP, Agus Amperianto menegaskan dan berkomitmen untuk penerapan safety di segala kegiatan operasi. Hal ini diungkapkan saat melakukan kunjungan lapangan atau Management Walktrough (MWT) di lapangan Tapen, Kecamatan Trucuk, Kabupaten Bojonegoro. 

    Dalam kunjungan tersebut General Manager Asset 4 Pertamina EP beserta jajaran manajemen Cepu Field memastikan pencapaian progres project Monetisasi sumur Gas TPN-01.

"Dari pengamatan saya di lapangan, secara progress konstruksi pembangunan EPF ini berlangsung lancar dan akan ditargetkan selesai pada akhir bulan Januari 2020," ujar Agus.

Lebih lanjut, Agus menambahkan, tujuan dilakukan MWT ini adalah untuk memastikan Output dari project monetisasi sumur TPN-01 dengan target produksi gas sebesar 1.8 MMSCFD. Dengan monetisasi gas dari kepala sumur ini diharapkan akan menambah revenue secara langsung untuk Pertamina EP Asset 4 Cepu Field. 

"Semoga semangat dan memotivasi pekerja Cepu Field dalam menyambut target kinerja Rencana Kerja Tahun 2020 Pertamina EP Asset 4 Cepu Field," ujarnya.

Agus Amperianto mengatakan target rencana ini diharapkan bisa mengoptimalkan peluang yang ada untuk bisa dieksekusi dengan baik, seperti project monetisasi gas yang sudah dilakukan di sumur Tapen ini. Dimana keberhasilan project ini akan mendukung pencapaian target produksi Field Cepu Tahun 2020 sebesar 2.206 BOPD. 

Kendati demikian, meskipun agresif dalam beroperasi tetap harus memastikan aspek safety berlangsung dengan baik dan Zero Incident tetap terjaga sesuai tema bulan K3 Pertamina EP tahun 2020 “Build Safety Behaviour? "Setinggi-tingginya capaian produksi kita, apabila terjadi Safety Failured maka itu semua tidak ada artinya. Maka mari kita semua baik pekerja maupun mitra kerja agar memperhatikan aspek Safety dalam bekerja," beber Agus Amperianto.

Sementara itu, Cepu Field Manager, Afwan Daroni mengaku, siap menyupport penuh arahan dan target yang telah disampaikan GM. Ia berjanji berkomitmen agar tahun 2020 ini pencapaian Kinerja Pertamina EP Asset 4 Cepu Field dapat lebih baik dan meningkat dari tahun-tahun sebelumnya. 

"Pastinya kami yang di Cepu juga akan berkomitmen sesuai arahan bapak GM," terangnya.

Harian Bangsa, Page-9, Tuesday, Jan 7, 2020

To Boost Oil and Gas Production, Pertamina Expands Four Oil and Gas Blocks



PT Pertamina (Persero) plans to expand the development of the four oil and gas blocks it manages domestically and internationally. This development is expected to increase the company's oil and gas production this year and in the future.

Pertamina Upstream Director Dharmawan H Samsu said, in the country, there are three termination oil and gas blocks which are the focus of the company's development namely the Mahakam, Sanga-Sanga, and East Kalimantan Blocks. 

the Sanga-Sanga block

    Although, the company will still intensively work on developing all termination blocks that have been assigned by the government. The three oil and gas blocks are the focus because their potential is still very good.

"The potential is still good. So we can apply a philosophy called creating a second cycle of the field, extended [production] age, "he said.

The development of these three oil and gas blocks through the Field Development Optimization Program (OPLL). Currently, it is proposing approval of the OPLL-1 Program for the Sanga-Sanga Block where 755 development wells will be drilled in this oil and gas block in the next 2-2.5 years.

     He hopes that drilling in the Sanga-Sanga Block can begin this year. However, the Sanga-Sanga Block development plan has not yet been approved because it also proposed economic project incentives. On the other hand, continued Dharmawan, Pertamina will also lower the economic limits of the project.

"But the government is given incentives such as additional split (revenue sharing), licensing that is facilitated, then leasing state assets are given a bonus bonus. This so that the gas can still be extracted at a lower cost so that the economy is maintained and the production is good, "he explained.

the Mahakam Block

For the Mahakam Block OPLL, approval of the development plan has been given by the Special Task Force for Upstream Oil and Gas Business Activities (SKK Migas). However, it also seeks to develop the Mahakam Block, which can also be given incentives by the government.

Earlier in its official statement, SKK Migas announced that PT Pertamina Hulu Mahakam would drill 257 wells in five fields in the Mahakam Block during the 2020-2022 period. Investment costs incurred in the amount of US $ 1.5 billion. Dharmawan continued, it will also run the OPLL Program in the East Kalimantan Block.

"Soon we also want to apply for PHPL OPLL [Pertamina Hulu East Kalimantan]. This [development plan] has not yet been submitted, we are
evaluation, "he said.

In the Mahakam Block, Pertamina will also drill two exploration wells. According to Dharmawan, these two wells namely Sumur Tunu Deep East and South Peciko. Well drilling will begin around July and is expected to increase the production of the Mahakam Block given the deeper drilling will take place where temperatures and pressures are very high.

"We expect to contribute around 30 million cubic feet per day / mmscfd from these two wells. But we must explore first, "he said.

Overseas Assets Pertamina also plans to expand oil and gas assets abroad, one of which is in Algeria. Dharmawan said that his party wanted to develop the Menzel Lejmet North (MLN) 2 oil and gas field. This field is an area around the MLN-1 Field which has now been managed by the company.

"That is what we want to propose for our expansion. We are still negotiating with the Government of Algeria through Sonatrach, Algeria's oil and gas BUMN, "he said.

He explained, the MLN-2 Field was a new oil and gas area which was not included in the MLN-1 Field. In this field, several exploration results have been discovered that Pertamina wants to develop.

But Dharmawan could not confirm whether an agreement with the Government of Algeria for the development of the MLN-2 Field could be reached in 2020. At present Pertamina, through its subsidiary, PT Pertamina International EP (PIEP), is the operator and holder of a majority management rights of 65% in the MLN Field.

Block 405A

This field is part of Block 405A where Pertamina also has management rights in two other fields, namely EMK Field 16.9% and Ourhoud Field 3.73%. At the end of 2017, Pertamina had signed a revised memorandum of understanding on the management of the oil and gas block in Algeria with Sonatrach.

Through this new agreement, the Algerian oil and gas company has opened opportunities for Pertamina to develop existing assets and work on new assets that have the potential to produce 20-30 thousand barrels per day (BPD) and total reserves of more than 100 million barrels of oil.

As is known, Pertamina is targeting oil and gas production in 2020 of 923 thousand barrels of oil equivalent per day / boepd, namely 430 thousand BPD of oil and 2,857 mmscfd of gas. According to Pertamina's data, the company's oil production is recorded to rise 3.85% from this year's target of 414 thousand BPD, while gas production is down 2.92% from the 2020 target of 2,943 mmscfd.

IN INDONESIA

Genjot Produksi Migas, Pertamina Ekspansi Empat Blok Migas


PT Pertamina (Persero) berencana mengekspansi pengembangan empat blok migas yang dikelolanya di dalam dan luar negeri. Pengembangan ini diharapkan bisa menambah produksi migas perseroan di tahun ini dan masa mendatang. 

Direktur Hulu Pertamina Dharmawan H Samsu menuturkan, di dalam negeri terdapat tiga blok migas terminasi yang menjadi fokus pengembangan perseroan yakni Blok Mahakam, Sanga-Sanga, dan East Kalimantan. Walaupun, perseroan tetap akan secara intensif mengerjakan pengembangan seluruh blok terminasi yang telah ditugaskan oleh pemerintah. Ketiga blok migas tersebut menjadi fokus lantaran potensinya masih sangat bagus.

“Potensinya masih bagus. Jadi kami bisa menerapkan filosofi yang disebut menciptakan siklus lapangan yang kedua, diperpanjang usia [produksinya],” katanya.

Pengembangan ketiga blok migas ini melalui Program Optimasi Pengembangan Lapangan-Lapangan (OPLL). Saat ini, pihaknya sedang mengajukan persetujuan Program OPLL-1 untuk Blok Sanga-Sanga di mana akan dilakukan pengeboran 755 sumur pengembangan di blok migas ini dalam 2-2,5 tahun ke depan. 

Pihaknya berharap pengeboran di Blok Sanga-Sanga bisa dimulai pada tahun ini. Namun, rencana pengembangan Blok Sanga-Sanga ini belum disetujui lantaran pihaknya juga mengusulkan insentif proyek ekonomis. Di sisi lain, lanjut Dharmawan, Pertamina juga akan menurunkan batasan keekonomian proyek tersebut.

“Tetapi dari pemerintah diberikan insentif misalnya tambahan split (bagi hasil), perizinan yang dipermudah, kemudian sewa aset negara diberi bonus diskon. Ini
supaya gasnya masih bisa diekstrak dengan biaya yang lebih rendah sehingga keekonomian terjaga dan produksinya baik,” papar dia.

Untuk OPLL Blok Mahakam, persetujuan rencana pengembangan telah diberikan oleh Satuan Kerja Khusus Pelaksana Kegiatan Usaha Hulu Minyak dan Gas Bumi (SKK Migas). Namun, pihaknya juga berupaya agar pengembangan Blok Mahakam ini juga dapat diberi insentif oleh pemerintah. 

Sebelumnya dalam keterangan resminya, SKK Migas mengumumkan bahwa PT Pertamina Hulu Mahakam akan mengebor 257 sumur di lima lapangan di Blok Mahakam selama periode 2020-2022. Biaya investasi yang dikeluarkan yakni sebesar US$ 1,5 miliar. Dharmawan melanjutkan, pihaknya juga akan menjalankan Program OPLL di Blok East Kalimantan. 

“Sebentar lagi kami juga mau mengajukan OPLL PHKT [Pertamina Hulu Kalimantan Timur]. Ini [rencana pengembangannya] belum di-submit, sedang kami evaluasi,” tuturnya.

Di Blok Mahakam, Pertamina juga akan mengebor dua sumur eksplorasi. Menurut Dharmawan, dua sumur ini yakni Sumur Tunu Deep East dan South Peciko. Pengeboran sumur akan dimulai sekitar Juli nanti dan diharapkan bisa menambah produksi Blok Mahakam mengingat pengeboran akan dilakukan lebih dalam di mana temperatur dan tekanannya sangat tinggi. 

“Kami harapkan bisa menyumbang sekitar 30 juta kaki kubik per hari/mmscfd dari dua sumur ini. Tetapi kami harus eksplorasi dulu,” ujar dia. 

Aset Luar Negeri Pertamina juga berencana melakukan ekspansi aset minyak dan gas di luar negeri, salah satunya di Aljazair. Dharmawan mengatakan, pihaknya ingin mengembangkan lapangan migas Menzel Lejmet North (MLN) 2. Lapangan ini merupakan area yang berada di sekitar Lapangan MLN-1 yang kini telah dikelola oleh perseroan.

“Itu mau kami propose untuk kami ekspansi. Kami masih negosiasi dengan Pemerintah Aljazair melalui Sonatrach, BUMN migas Aljazair,” tutur dia.

Dijelaskannya, Lapangan MLN-2 merupakan area migas baru yang tidak termasuk dalam Lapangan MLN-1. Di lapangan ini, telah ditemukan beberapa hasil eksplorasi yang ingin dikembangkan Pertamina. 

Namun Dharmawan tidak dapat memastikan apakah kesepakatan dengan Pemerintah Aljazair untuk pengembangan Lapangan MLN-2 bisa tercapai pada tahun 2020 ini. Saat ini Pertamina melalui anak usahanya, PT Pertamina International EP (PIEP), menjadi operator sekaligus pemegang hak kelola mayoritas sebesar 65% di Lapangan MLN. 

Lapangan ini merupakan bagian dari Blok 405A di mana Pertamina juga memiliki hak kelola di dua lapangan lainnya yakni Lapangan EMK 16,9% dan Lapangan Ourhoud 3,73%. Pada akhir 2017, Pertamina sempat meneken revisi nota kesepahaman pengelolaan blok migas di Aljazair dengan Sonatrach. 

Melalui kesepakatan baru ini, perusahaan migas milik Aljazair itu membuka peluang bagi Pertamina untuk mengembangkan aset eksisting serta mengerjakan aset baru yang memiliki potensi produksi 20-30 ribu barel per hari (bph) dan total cadangan lebih dari 100 juta barel minyak. 

Seperti diketahui, Pertamina menargetkan produksi migas pada tahun 2020 ini sebesar 923 ribu barel setara minyak per hari/boepd, yakni minyak 430 ribu bph dan gas 2.857 mmscfd. Sesuai data Pertamina, produksi minyak perseroan tercatat naik 3,85% dari target tahun ini 414 ribu bph, sementara produksi gas turun 2,92% dari target tahun 2020 ini 2.943 mmscfd.

Investor Daily, Page-9, Monday, Jan 6, 2020

Tuban Refinery Built, Residents Do Not Become Spectators



Republic of Indonesia House of Representatives Commission VII (DPR RI) of the Electoral District of Tuban-Bojonegoro, Rama Juwita Sari hopes that the public will not become spectators When the Rosneft Tuban oil refinery is established. 


"Rama Juwita Sari, at least 70 percent of Tuban residents must participate and work in the Pertamina company which is in the commission of VII. They continue to convey that local workers must be employed at least 70 percent of local residents," said Rama Juwita.

She added the establishment of the Tuban refinery needs to be welcomed by the community. The reason is, if it has already been built it will reduce oil imports by 30 percent. On the other hand, the economy of the Tuban Regency will automatically progress and develop. Seeing these conditions the community should improve so that the existence of the Tuban refinery has a positive impact.

"If so far there are still those who refuse, the local government should immediately sit together to talk from day to day and find the best solution," said Rama Juwita Sari.

This DPR RI member said, if the problem of rejection continues to drag on, it will be exploited by individuals who are only looking for profit. Therefore, it is better if the Tuban District Government and the refusing community need to sit together.

"Do not let this problem drag on, let alone be exploited by persons who only seek personal gain," said Rama Juwita Sari.

Meanwhile, for the sake of residents being able to work at the Tuban refinery, the Regency Government should bridge by making training and skills training. In fact, Commission VII is currently continuing to encourage the Ministry of Energy and Mineral Resources and Oil and Gas SKK to immediately create an Oil and Gas Vocational High School (SMK) in Tuban Regency.

IN INDONESIA

Kilang Tuban Dibangun, Warga Jangan Jadi Penonton


Anggota DPR RI Komisi VII Daerah Pemilihan Tuban-Bojonegoro, Rama Juwita Sari berharap, kepada masyarakat agar tidak menjadi penonton Saat kilang minyak Rosneft Tuban berdiri. 

     Rama Juwita Sari , minimal 70 persen warga Tuban harus ikut serta dan bekerja di perusahaan pertamina itu yang berada dikomisi VII terus menyampaikan agar tenaga kerja lokal harus dipekerjakan minimal 70 persen dari warga lokal," ujar Rama Juwita.

Rama Juwita menambahkan, berdirinya kilang Tuban ini perlu disambut oleh masyarakat. Pasalnya, bila sudah dibangun maka akan mengurangi impor minyak sebanyak 30 persen. 

    Di sisi lain, perekonomian Kabupaten Tuban secara otomatis akan maju dan berkembang. Melihat kondisi tersebut sebaiknya masyarakat perlu improvisasi agar keberadaan kilang Tuban ini memberikan dampak positif. 

"Jika selama ini masih ada yang menolak, sebaiknya pemerintah setempat segera duduk bersama berbicara dari hari ke hari dan temukan solusi yang terbaik," tutur Rama Juwita Sari.

Anggora DPR RI ini menuturkan, jika permasalahan penolakan masih terus berlarut, maka akan dimanfaatkan oleh oknum-oknum yang hanya mencari keuntungan. Oleh sebab itu, sebaiknya antara Pemerintah Kabupaten Tuban dan masyarakat penolak kilang perlu duduk bersama.

"Jangan sampai permasalahan ini berlarut-larut, apalagi dimanfaatkan oleh oknum-oknum yang hanya mencari keutungan pribadi," kata Rama Juwita Sari.

Sementara itu, demi warga dapat bekerja di kilang Tuban, sebaiknya Pemerintah Kabupaten menjembatani dengan membuat pelatihan-pelatihan dan training keahlian. 

     Bahkan, Komisi VII saat ini terus mendorong Kementerian ESDM dan SKK Migas agar segera membuat Sekolah Menengah Kejuruan (SMK) Minyak dan Gas di Kabupaten Tuban.

Harian Bangsa, Page-9, Monday, Jan 6, 2020.

Encouraging the Development of Oil and Gas Block



Earlier this year, the national oil and gas sector began to run fast. This can be seen from the hard work of the Special Task Force for Upstream Oil and Gas Business Activities (SKK Migas) in encouraging the development of three oil and gas blocks, namely the Sanga Sanga Block in East Kalimantan, the South Sumatra Sakakemang Block, and the South Sumatra Merakes Field.

the Sanga Sanga Block

The development aims to boost the lifting of 1 million barrels of crude oil per day (BPD). Based on SKK Migas data, up to 30 December 2019, Indonesia's oil lifting was only reached 735,219 barrels per day (BPD) or 94.87% of the target of the State Budget (APBN).



Meanwhile, gas lifting was only reached 5,934 million cubic feet per day / MMscfd or 84.77% of the APBN target. The development of these three regions is like fresh air in the world of oil and gas. The amount of reserves contained in the three oil and gas blocks is expected to drive the achievement of the lifting target.

Based on an evaluation conducted by SKK Migas, the operator in the Sanga-Sanga Block namely Pertamina Hulu Sanga-Sanga has proposed drilling 755 new wells. The Sanga-Sanga block is projected to have 1.2 trillion cubic feet / Tcf of gas and 84.3 million barrels of oil / MMbo. 

Lemigas

     Meanwhile, field development in the Sakakemang Block is still awaiting the issuance of 1 Tcf proven reserve certification from the Center for Research and Development of Oil and Gas Technology (Lemigas).

Repsol

Repsol, as the operator of Sakakemang Block, has just submitted a certification of proven reserves of 1 Tcf from the potential of proven reserves of 2 Tcf. The discovery of 2 Tcf of gas reserves came from the Kaliberau Dalam ZX well. If the reserve certification from Lemigas has been obtained, Repsol can directly develop the Work Area in the first quarter / 2020. Meanwhile, the production process can begin in 2021.

the Merakes field

On the contrary, currently, the Merakes field development plan has been approved by SKK Migas. Eni East Sepinggan Ltd, the operator of the East Sepinggan Block, said that gas reserves in the Merakes Field are estimated to reach 2 Tcf.

The government's strategy to encourage the development of a number of working areas cannot be separated from efforts to maintain the risk of increasing the deficit in the state budget due to oil and gas lifting targets that have not been achieved in recent years. 

     Not only that, but the government is also trying to spur oil and gas cooperation contract contractors (KKKS) who have old oil and gas wells to use the Enhanced Oil Recovery (EOR) technique. The use of this high technology to withstand the decline in natural production from a number of wells.

Oil and gas KKKS that use EOR technology will receive incentives from the government so that the economic value of the project can be maintained. In addition, the government also seeks to create a conducive investment climate so that oil and gas investors enter Indonesia.

A number of strategies taken by the government to encourage national oil and gas production are important to achieve because the community's need for energy sources is still very large. 

     However, all the efforts made by the government will not succeed without the support of stakeholders in the oil and gas industry. New innovations from investors used to explore potential areas need to achieve increased national oil and gas production.

IN INDONESIA

Mendorong Pengembangan Blok Migas

Awal tahun ini, sektor minyak dan gas nasional mulai berlari kencang. Hal ini dapat dilihat dari upaya keras Satuan Kerja Khusus Pelaksana Kegiatan Usaha hulu Minyak dan Gas Bumi (SKK Migas) dalam mendorong pengembangan tiga blok migas, yakni Blok Sanga Sanga Kalimantan Timur, Blok Sakakemang Sumatra Selatan, dan Lapangan Merakes Sumatra Selatan. 

Pengembangan tersebut bertujuan menggenjot lifting minyak mentah 1 juta barel per hari (bph). Berdasarkan data SKK Migas, hingga 30 Desernber 2019, lifting minyak Indonesia hanya tercapai 735.219 barel per hari (bph) atau 94,87% dari target Anggaran Pendapatan dan Belanja Negara (APBN).

Adapun, lifting gas hanya tercapai 5.934 juta kaki kubik per hari/MMscfd atau 84,77% dari target APBN. Pengembangan dari tiga wilayah tersebut tidak ubahnya angin segar di dunia minyak dan gas. Jumlah cadangan yang terkandung di tiga blok minyak dan gas tersebut diharapkan dapat mendorong pencapaian target lifting.

Berdasarkan evaluasi yang dilakukan SKK Migas, operator di Blok Sanga-Sanga yakni Pertamina Hulu Sanga-Sanga telah mengajukan pengeboran 755 sumur baru. Blok Sanga-Sanga diproyeksikan memiliki 1,2 triliun kaki kubik/Tcf gas dan 84,3 juta barel minyak/MMbo. 

    Sementara itu, untuk pengembangan lapangan di Blok Sakakemang masih menunggu penerbitan sertifikasi cadangan terbukti 1 Tcf dari Pusat Penelitian dan Pengembangan Teknologi Minyak dan Gas Bumi (Lemigas).

Repsol, sebagai operator Blok Sakakemang, baru saja mengajukan sertifikasi cadangan terbukti sebesar 1 Tcf dari potensi cadangan terbukti 2 Tcf. Penemuan cadangan gas sebesar 2 Tcf tersebut berasal dari sumur Kaliberau Dalam ZX. 

     Jika sertifikasi cadangan dari Lemigas sudah didapatkan maka Repsol bisa langsung mengembangkan Wilayah Kerjanya tersebut pada kuartal I/2020. Sementara itu, proses produksi dapat dimulai pada 2021.

Sebaliknya, saat ini rencana pengembangan lapangan Merakes telah disetujui oleh SKK Migas. Eni East Sepinggan Ltd, operator Blok East Sepinggan, menyatakan bahwa cadangan gas di Lapangan Merakes diperkirakan rnencapai 2 Tcf. 

Strategi pemerintah untuk mendorong pengembangan sejumlah wilayah kerja ini tidak lepas dari upaya menjaga risiko peningkatan defisit dalam APBN akibat target lifting migas yang beberapa tahun ini tidak tercapai. 

    Tidak cukup hanya itu, pemerintah juga berupaya memacu kontraktor kontrak kerja sama (KKKS) migas yang memiliki sumur migas tua untuk menggunakan teknik Enhanced Oil Recovery (EOR). Penggunaan teknologi tinggi ini untuk menahan penurunan produksi alami dari sejumlah sumur.

KKKS migas yang menggunakan teknologi EOR akan mendapatkan insentif dari pemerintah, sehingga nilai keekonomian proyek dapat terjaga. Selain itu, pemerintah juga berupaya menciptakan iklim investasi yang kondusif agar investor migas yang masuk ke Indonesia bertambah. 

Sejumlah strategi yang diambil pemerintah untuk mendorong produksi migas nasional tersebut menjadi penting untuk dicapai, karena kebutuhan masyarakat terhadap sumber energi masih sangat besar. 

     Namun, seluruh upaya yang dilakukan oleh pemerintah tersebut tidak akan berhasil tanpa dukungan para pihak yang berkepentingan di industri migas. Inovasi baru dari investor yang digunakan untuk mengeksplorasi area potensial perlu untuk mencapai peningkatkan produksi migas nasional.

Bisnis Indonesia, Page-2, Monday, Jan 6, 2020.

Pertamina Immediately Operates Rokan



From 72 wells, Pertamina will drill 20 wells.

PT Pertamina (Persero) will begin drilling in the Rokan Block in Riau Province in the third quarter of 2020. The government requests the current Rokan Block operators and future operators to coordinate well. Pertamina Upstream Director Dharmawan Samsu explained, this acceleration step needed to be done to maintain the production of the Rokan Block.

the Rokan Block Chevron Indonesia

"This is very important because we need to make sure in 2020 we can really do the drilling," Dharmawan said.

Chevron

To do the drilling, there are several conditions agreed upon between the prospective new operators, namely Pertamina and the old operators. namely Chevron. This is to maintain investment in the transition period. Darmawan explained naturally the reserves in the reservoir will continue to decline. To overcome this, Pertamina needs to drill. The plan is, to begin with, Pertamina will drill 20 wells.

"Yes, these are steps that need to be taken apart from the need to maintain wells, maintain compression, and maintain production stability," Dharmawan said.

To get to the drilling schedule in the third quarter, Dharmawan explained, in the first half of this year, Pertamina needed to make preparations for procurement. These include long lead items such as rig readiness and wheel heads (wells to be drilled).

"In the first semester, we focus on providing goods for drilling. We want to ensure that the rig and crew are ready," Dharmawan said.

With this drilling plan, Darmawan said, it was possible that there would be a revision of the company's Work and Budget Plan (RKP & B). These changes will be discussed with the Special Task Force for Upstream Oil and Gas Business Activities (SKK Migas), including production and investment targets.


"SKK Migas is very supportive and conducive. They ensure that all initiatives to maintain production will be supported," Darmawan said.

In the WP&B 2020 SKK Migas, Rokan Block oil production is targeted at 161 thousand barrels per day (BPH). In 2018, this block can still produce 210 thousand BPD, the second largest after Cepu Block oil production.

Arifin Tasrif

ESDM Minister Arifin Tasrif said Pertamina planned to drill 20 wells in the Rokan Block by 2020. In total, 72 wells were planned. Even so, Arifin did not specify the investment value to be spent by the government oil and gas company in the Rokan Block.

"Of the 72 targets, at least 20 can be implemented next year. It could be faster," Arifin said when meet at the BPH Migas Building.

Arifin has also asked Pertamina to be more proactive in order to smooth the transition process in the Rokan Block to run smoothly. He appealed to Chevron as the current manager not to close down when Pertamina entered before the Chevron contract in the Rokan Block expires in 2021. Therefore, Arifin hopes that discussions between Pertamina and Chevron regarding the transition in the Rokan Block can soon be completed in the near future.

"Chevron reports every week, there are matters relating to regulations and contractual rights," Arifin said.

Since it was first discovered in 1941 to date, the Rokan Block has produced approximately 4.5 billion barrels of oil. It is estimated that the Rokan Block currently still holds 500 million to 1.5 billion barrels of oil.

As for 2020, SKK Migas set a production target in the Rokan Block of only 161 thousand bopd, down from this year's target of 190 thousand bopd. That is because there is no activity that will be carried out by Chevron in the Rokan Block in 2021.

IN INDONESIA

Pertamina Segera Operasikan Rokan


Dari 72 sumur, Pertamina akan mengebor 20 sumur.

PT Pertamina (Persero) akan mulai melakukan pengeboran di Blok Rokan di Provinsi Riau pada kuartal III tahun 2020 ini. Pemerintah meminta operator Blok Rokan saat ini dan operator ke depan dapat berkoordinasi dengan baik. Direktur Hulu Pertamina Dharmawan Samsu menjelaskan, langkah percepatan ini perlu dilakukan untuk menjaga produksi Blok Rokan. 

"Ini penting sekali karena kami perlu meyakinkan pada 2020 kami betul-betul bisa melakukan pengeboran," ujar Dharmawan.

Untuk melakukan pengeboran, ada beberapa ketentuan yang disepakati antara calon operator baru, yakni Pertamina dengan operator lama. yakni Chevron. Hal ini untuk menjaga lnvestasi di masa transisi. Darmawan menjelaskan secara alamiah cadangan dalam reservoar akan tetap mengalami penurunan. Untuk bisa mengatasi hal tersebut, Pertamina perlu melakukan pengeboran. Rencananya, untuk awalan, Pertamina akan mengebor 20 sumur.

"Ya ini langkah-langkah yang perlu dilakukan selain perlu melakukan perawatan sumur, menjaga kompresi, dan menjaga stabilan produksi," ujar Dharmawan.

Untuk menuju jadwal pengeboran pada kuartal tiga tersebut, Dharmawan menjelaskan, pada semester pertama tahun ini, Pertamina perlu melakukan persiapan pengadaan. Pengadaan tersebut antara lain adalah long lead item seperti kesiapan rig dan wheel head (kepala sumur untuk bisa dibor).

"Semester satu kami fokus melakukan penyediaan barang untuk pengeboran. Kami mau memastikan rig dan kru siap," ujar Dharmawan.

Dengan rencana pengeboran ini, Darmawan mengatakan, tidak menutup kemungkinan bakal ada revisi Rencana Kerja dan Anggaran (RKP&B) perusahaan. Perubahan-perubahan ini akan dibicarakan dengan Satuan Kerja Khusus Pelaksana Kegiatan Usaha Hulu Minyak dan Gas Bumi (SKK Migas), termasuk target produksi dan investasi.

"SKK Migas sangat suportif dan kondusif. Mereka memastikan semua inisiatif menjaga produksi akan didukung," ujar Darmawan.

Dalam WP&B 2020 SKK Migas, produksi minyak Blok Rokan ditargetkan sebanyak 161 ribu barel per hari (BPH). Pada 2018, blok ini masih bisa produksi 210 ribu bph atau kedua terbesar setelah produksi minyak Blok Cepu. 

Menteri ESDM Arifin Tasrif mengatakan, Pertamina berencana melakukan pengeboran sumur di Blok Rokan sebanyak 20 sumur pada 2020. Secara total, target yang dicanangkan sebanyak 72 sumur. Meski begitu, Arifin tidak memerinci nilai investasi yang akan dikeluarkan oleh perusahaan minyak dan gas mili pemerintah tersebut di Blok Rokan.

"Dari 72 target, paling tidak 20 itu bisa terlaksana di tahun depan. Bisa lebih cepatlah," kata Arifin saat ditemui di Gedung BPH Migas.

Arifin pun sudah meminta Pertamina untuk lebih proaktif guna memuluskan proses transisi di Blok Rokan berlangsung lancar. Ia mengimbau Chevron selaku pengelola saat ini agar tidak menutup diri ketika Pertamina masuk sebelum kontrak Chevron di Blok Rokan berakhir pada 2021. Maka itu, Arifin berharap, agar diskusi antara Pertamina dan Chevron terkait transisi di Blok Rokan dapat segera rampung dalam waktu dekat. 

"Tiap minggu Chevron sudah lapor, ada hal-hal yang terkait regulasi maupun hak-hak kontraktual," ujar Arifin.

Sejak ditemukan pertama kali pada 1941 sampai saat ini, Blok Rokan telah menghasilkan kurang lebih 4,5 miliar barel minyak. Diperkirakan saat ini Blok Rokan masih menyimpan 500 juta hingga 1,5 miliar barel minyak. 

Adapun pada tahun 2020, SKK Migas mematok target produksi di Blok Rokan hanya sebesar 161 ribu bopd atau turun dibandingkan target tahun ini yang sebesar 190 ribu bopd. Hal tersebut karena tidak ada aktivitas apa pun yang bakal dilaksanakan Chevron di Blok Rokan pada tahun 2021.

Republika, Page-5, Saturday, Jan 4, 2020.

In the third quarter, Pertamina is targeting to work on the Rokan Block




PT Pertamina (Persero) is targeting to participate in spending funds to work on the Rokan Block starting the third quarter of 2020. The reason is, until now, Pertamina is still discussing with PT Chevron Pacific Indonesia (CPI) related to the participation in working on the Rokan Block during the transfer period.

the Rokan Block Chevron

Pertamina Upstream Director Dharmawan H Samsu said discussions with Chevron had stopped for two weeks at the end of last year. However, he will continue this discussion on Monday (6 / January).

The discussion progress has been fixed on Pertamina's participation in working on the Rokan Block this year. However, he admitted, Pertamina had not been able to get involved in investing in the Rokan Block in the first half of 2020. Because, it requires time to provide the goods needed for drilling, such as rigs and wellheads, as well as the crew who will carry out this activity.

"We need to make sure the rig is ready, prepare the crew, ensure that long lead items such as the wellhead are prepared. So drilling in the third quarter, "he said in Jakarta.

Dharmawan explained that the agreement relating to the transfer of management of the Rokan Block was very important for Pertamina. This is because, in order to carry out well drilling, there are a number of prerequisites that must be agreed by the two oil and gas companies. Pertamina also needs to maintain investment in the transition period so that oil and gas production from the Rokan Block does not drop dramatically.

"The reservoir will naturally come down. To counter this decline, we are drilling, in addition to efforts to maintain the well, maintain compression, "he said.

Regarding the number of wells to be drilled, his party has not confirmed it yet. However, he estimates that at least 20 new development wells will be drilled to maintain the level of oil and gas production and curb the rate of decline in natural production. The number of wells drilled can still change.

"There could be more [wells drilled], but we cannot determine more yet. This drilled 20 wells so that production did not go down, "Dharmawan explained.

If he becomes involved in investing in the Rokan Block, Dharmawan claims that he does not know whether the work plan and budget (WP & B) The Rokan Block must be revised. It will continue to discuss with the Special Task Force for Upstream Oil and Gas Business Activities (SKK Migas) related to this matter.

"SKK Migas is very supportive and conducive, all initiatives that maintain oil and gas production will definitely be supported," he said.

Previously, SKK Migas Head Dwi Soetjipto revealed that the Rokan Block oil production target in 2020 was set at only 161 thousand barrels per day (BPD). This target is down 15.26% from this year's production target of 190 thousand BPD.

Because Chevron reduced its operational activities following the end of the Rokan Block / PSC cooperation contract in 2021. The WP&B Block Rokan, he said, only included Chevron's planned activities, not Pertamina. He hopes that Pertamina can immediately participate in working on the Rokan Block.

"It is hoped that Pertamina can enter to conduct drilling, it is hoped that it can improve what is included in WP&B," Dwi said.

During its heyday in 1973, Rokan Block's oil production nearly touched 1 million BPD. However, oil and gas block production continues to fall over time. In 2011, the Rokan Block still produced around 356.98 thousand BPD of oil or contributed 39.56% of the total national oil production at that time 902.35 BPD.

However, referring to SKK Migas data, at the end of September 2019, the oil lifting of this block was only 192,193 BPD or 25.8% of the total national oil lifting of 744,700 BPD. The government has set Pertamina as the operator of the Rokan Block after the current contract will expire in 2021. 

    However, the Rokan Block PSC contract for the period after 2021, was just signed by Pertamina in May 2019. The transition process for the management of the Rokan Block has just taken place after the contract just signed.

Referring to this new contract, Pertamina has a definite work commitment (KKP) for the first five years in the Rokan Block worth the US $ 500 million or around Rp 7.2 trillion. Some of the activities to be funded by the CTF include an EOR study of US $ 4 million, drilling of 11 exploration wells of US $ 69.8 million, drilling of five Telisa wells of US $ 18.1 million, stage-1 CEOR 7 pattern of US $ 247 million, and stage-1 steam flood Kulin or Rantau Bais US $ 88.6 million.

IN INDONESIA

Kuartal III, Pertamina Targetkan Ikut Garap Blok Rokan

PT Pertamina (Persero) menargetkan dapat ikut serta mengeluarkan dana untuk menggarap Blok Rokan mulai kuartal ketiga 2020 ini. Pasalnya, hingga kini, Pertamina masih berdiskusi dengan PT Chevron Pacific Indonesia (CPI) terkait keikutsertaan menggarap Blok Rokan di masa alih kelola. 

Direktur Hulu Pertamina Dharmawan H Samsu menuturkan, diskusi dengan Chevron sempat berhenti selama dua pekan pada akhir tahun lalu. Namun, pihaknya akan melanjutkan diskusi ini pada Senin (6/January). 

Progres diskusi telah fix pada keikutsertaan Pertamina menggarap Blok Rokan pada tahun ini. Meski demikian, diakuinya, Pertamina belum dapat ikut terlibat berinvestasi di Blok Rokan pada semester pertama 2020 ini. 

   Pasalnya, pihaknya membutuhkan waktu untuk menyediakan barang yang dibutuhan untuk pengeboran, seperti rig, dan kepala sumur, serta kru yang akan melaksanakan kegiatan ini.

“Kami perlu memastikan rig siap, menyiapkan kru, memastikan bahwa long lead item seperti well head disiapkan. Jadi pengeboran pada kuartal tiga,” kata dia di Jakarta.

Dharmawan menjelaskan, kesepakatan terkait masa alih kelola Blok rokan sangat penting bagi Pertamina. Hal ini lantaran agar dapat melaksanakan pengeboran sumur, terdapat beberapa prasyarat yang harus disepakati oleh kedua perusahaan migas. Pertamina juga perlu menjaga investasi di masa transisi agar produksi migas dari Blok Rokan tidak turun drastis.

“Reservoir itu akan secara alamiah turun. Untuk mengcounter penurunan ini, kami melakukan pengeboran, di samping upaya-upaya merawat sumur, menjaga kompresi,” ujarnya.

Terkait jumlah sumur yang akan dibor, pihaknya belum ada memastikannya. Namun, pihaknya memperkirakan setidaknya dibutuhkan pengeboran 20 sumur pengembangan baru untuk menjaga level produksi migas dan menahan laju penurunan produksi alamiahnya. Jumlah sumur yang dibor ini masih dapat berubah.

“Bisa lebih banyak lagi [sumur yang dibor], tetapi kami belum bisa menentukan lebih banyaknya. Ini  mengebor 20 sumur agar produksi tidak turun,” jelas Dharmawan.

Jika jadi ikut terlibat berinvestasi di Blok Rokan, Dharmawan mengaku tidak mengetahui apakah rencana kerja dan belanja (work plan and budget/WP&B)
Blok Rokan harus direvisi. Pihaknya akan terus berdiskusi dengan Satuan Kerja Khusus Pelaksana Kegiatan Usaha Hulu Minyak dan Gas Bumi (SKK Migas) terkait hal ini. 

“SKK Migas sangat suportif dan kondusif, semua inisiatif yang menjaga produksi migas pasti akan didukung,” tutur dia.

Sebelumnya, Kepala SKK Migas Dwi Soetjipto mengungkapkan, target produksi minyak Blok Rokan pada 2020 ini ditetapkan hanya 161 ribu barel per hari (bph). Target ini turun 15,26% dari target produksi tahun ini sebesar 190 ribu bph. 

Pasalnya, Chevron mengurangi aktifitas operasinya menyusul berakhirnya kontrak kerja sama/PSC Blok Rokan pada 2021. WP&B Blok Rokan disebutnya hanya memasukkan rencana kegiatan Chevron, belum Pertamina. Pihaknya berharap Pertamina bisa segera ikut serta menggarap Blok Rokan. 

“Diharapkan Pertamina bisa masuk untuk melakukan drilling, diharapkan bisa memperbaiki apa yang masuk dalam WP&B,” ujar Dwi.

Pada masa kejayaannya di 1973, produksi minyak Blok Rokan hampir menyentuh 1 juta bph. Namun, produksi blok migas ini terus turun seiring berjalannya waktu. Di 2011, Blok Rokan masih menghasilkan minyak sekitar 356,98 ribu bph atau berkontribusi 39,56% dari total produksi minyak nasional saat itu 902,35 bph. 

Namun mengacu data SKK Migas, di akhir September 2019 lalu, lifting minyak blok ini hanya192.193 bph atau 25,8% dari total lifting minyak nasional 744.700 bph. Pemerintah telah menetapkan Pertamina sebagai operator Blok Rokan pasca kontrak yang saat ini berlaku akan berakhir pada 2021. 

    Namun, kontrak PSC Blok Rokan untuk periode setelah 2021, baru saja ditandatangani oleh Pertamina pada Mei tahun 2019. Proses transisi pengelolaan Blok Rokan baru saja berlangsung pasca kontrak baru ditandatangani. 

Mengacu kontrak baru ini, Pertamina memiliki komitmen kerja pasti (KKP) untuk lima tahun pertama di Blok Rokan senilai US$ 500 juta atau sekitar Rp 7,2 triliun. Beberapa kegiatan yang akan didanai dengan KKP ini yakni studi EOR senilai US$ 4 juta, pengeboran 11 sumur eksplorasi US$ 69,8 juta, pengeboran lima sumur Telisa US$ 18,1 juta, stage-1 CEOR 7 pattern US$ 247 juta, dan stage-1 steam flood Kulin atau Rantau Bais US$ 88,6 juta.

Investor Daily, Page-9, Saturday, Jan 4, 2020.